== 6.1 Short term seismic hazard assessment ==
== 6.1 Short term seismic hazard assessment ==


=== 6.1.1 Short term seismic hazard assesment – basic ===
=== 6.1.1 Basic ===


For the analysis of seismic responses after blasts and large events, the basic approaches include the qualitative assessment of a time series chart (e.g. magnitude-time, daily histogram, cumulative event count) and spatial plot of seismicity (e.g. plan view, 3D view). This style of analysis is done on the vast majority of sites irrespective whether more advanced approaches are also considered. Figure 33 provides an example of a seismic response to a large event. Spatial plot is shown left and an annotated time series is shown right (Vallejos and McKinnon 2010).
For the analysis of seismic responses after blasts and large events, the basic approaches include the qualitative assessment of a time series chart (e.g. magnitude-time, daily histogram, cumulative event count) and spatial plot of seismicity (e.g. plan view, 3D view). This style of analysis is done on the vast majority of sites irrespective whether more advanced approaches are also considered. Figure 33 provides an example of a seismic response to a large event. Spatial plot is shown left and an annotated time series is shown right (Vallejos and McKinnon 2010).
Line 27: Line 27:
Figure 34 Diurnal chart of seismic and blast activity (Vallejos and McKinnon 2010)
Figure 34 Diurnal chart of seismic and blast activity (Vallejos and McKinnon 2010)


=== 6.1.2 Short term seismic hazard assesment – advanced ===
=== 6.1.2 Advanced ===


Advanced analysis of seismic responses incorporates seismic source parameters into the assessment and/or aims to quantify the space-time characteristics of a response.  
Advanced analysis of seismic responses incorporates seismic source parameters into the assessment and/or aims to quantify the space-time characteristics of a response.  
Line 56: Line 56:
== 6.2 Re-entry analysis ==
== 6.2 Re-entry analysis ==


=== 6.2.1 Re-entry analysis – basic ===
=== 6.2.1 Basic ===


The topic of re-entry is covered in two sections. This section focuses on the analysis of data following blasts and large events and the derivation of rules. The application of these rules and real-time monitoring of seismicity and re-entry decisions is discussed under the Control section (10.1.2).
The topic of re-entry is covered in two sections. This section focuses on the analysis of data following blasts and large events and the derivation of rules. The application of these rules and real-time monitoring of seismicity and re-entry decisions is discussed under the Control section (10.1.2).
For many sites, re-entry protocols are not based on back analysis of seismicity, but rather on choosing conservative re-entry periods. Some sites with enough flexibility in the mining schedule allow long periods before re-entry by sheduling work to be performed in areas further away from recent blasts.
For many sites, re-entry protocols are not based on back analysis of seismicity, but rather on choosing conservative re-entry periods. Some sites with enough flexibility in the mining schedule allow long periods before re-entry by sheduling work to be performed in areas further away from recent blasts.


=== 6.2.2 Re-entry analysis – advanced ===
=== 6.2.2 Advanced ===


Re-entry analysis uses short-term assessment techniques to characterise current and/or historical seismic responses. Blanket exclusion rules are developed from historical responses and consider practical operational constraints. These rules are typically conservative by design and use the assessment of a current seismic response to refined exclusions.  
Re-entry analysis uses short-term assessment techniques to characterise current and/or historical seismic responses. Blanket exclusion rules are developed from historical responses and consider practical operational constraints. These rules are typically conservative by design and use the assessment of a current seismic response to refined exclusions.  
Line 70: Line 70:
== 6.3 Medium/long term hazard assessment ==
== 6.3 Medium/long term hazard assessment ==


=== 6.3.1 Medium/long term hazard assessment – basic ===
=== 6.3.1 Basic ===


Seismic hazard over the longer term is generally reported using simple statistics. Weekly and monthly reports usually include the total number of events recorded, as well as the number of large/significant events. Sometimes the event count over the previous reporting periods is included for reference.
Seismic hazard over the longer term is generally reported using simple statistics. Weekly and monthly reports usually include the total number of events recorded, as well as the number of large/significant events. Sometimes the event count over the previous reporting periods is included for reference.
Line 92: Line 92:
Table 4 Qualitative seismic hazard scale (Hudyma and Potvin 2004)
Table 4 Qualitative seismic hazard scale (Hudyma and Potvin 2004)


=== 6.3.2 Medium/long term hazard assessment – advanced ===
=== 6.3.2 Advanced ===
 
Although the investigation into pre-cursors to earthquakes and mining-induced seismic events are continuing, it is well recognised that meaningful predictions of large seismic seismic events are not currently possible. Given the inherent variability and uncertainty of mining seismicity, results from advanced seismic hazard assessments are often probabilistic (Figure 41).
Although the investigation into pre-cursors to earthquakes and mining-induced seismic events are continuing, it is well recognised that meaningful predictions of large seismic seismic events are not currently possible. Given the inherent variability and uncertainty of mining seismicity, results from advanced seismic hazard assessments are often probabilistic (Figure 41).


Line 120: Line 121:
== 6.4 Medium/long term source characterisation ==
== 6.4 Medium/long term source characterisation ==


=== 6.4.1 Medium/long term source characterisation – basic ===
=== 6.4.1 Basic ===


It is important for the site geotechnical team to form an appreciation of the different sources of seismicity in the mine, their characteristics and their likely response to mining activity. This appreciation is obtained through back-analysis and detailed investigation into the recorded seismic and non-seismic data, interpreting different source parameters within the context of mining. In spite of its importance, this is not commonly done.
It is important for the site geotechnical team to form an appreciation of the different sources of seismicity in the mine, their characteristics and their likely response to mining activity. This appreciation is obtained through back-analysis and detailed investigation into the recorded seismic and non-seismic data, interpreting different source parameters within the context of mining. In spite of its importance, this is not commonly done.
Line 126: Line 127:
Some operations use the S:P energy ratio as an indication of seismic mechanism. High ratios, in theory, indicate a stronger shearing/deviatoric mechanism while lower ratios indicate a more crushing/ bursting/isotropic mechanism. Recent research has raised some doubt over the reliability of the S:P energy ratio parameter (Morkel et al. 2017 Under review).
Some operations use the S:P energy ratio as an indication of seismic mechanism. High ratios, in theory, indicate a stronger shearing/deviatoric mechanism while lower ratios indicate a more crushing/ bursting/isotropic mechanism. Recent research has raised some doubt over the reliability of the S:P energy ratio parameter (Morkel et al. 2017 Under review).


=== 6.4.2 Medium/Long term source characterisation – advanced ===
=== 6.4.2 Advanced ===


Methods used for medium/long term characterisation of seismic sources analyse seismic data in order to gain insight into the rock mass response to mining; either causation or mechanism of rock mass deformation.  
Methods used for medium/long term characterisation of seismic sources analyse seismic data in order to gain insight into the rock mass response to mining; either causation or mechanism of rock mass deformation.  
Line 141: Line 142:
Figure 45 Grid-based analysis of EI and Seismic Displacement (Wesseloo et al. 2014)
Figure 45 Grid-based analysis of EI and Seismic Displacement (Wesseloo et al. 2014)


=== 6.5.1 SGM interpolation – basic ===
== 6.5 SGM interpolation ==
 
=== 6.5.1 Basic ===


Strong ground motion (PPV or PPA) is often used as a parameter for seismic hazard intensity. The derivation of site-specific relationships is required. This is becoming more common, but is not performed on all sites, with some sites using generic relationships presented in literature. Using the strong ground motion relationship and the properties of an event, the theoretical strong ground motion experienced at an excavation is often calculated to assess the effect of large remote events on excavation (Figure 46).
Strong ground motion (PPV or PPA) is often used as a parameter for seismic hazard intensity. The derivation of site-specific relationships is required. This is becoming more common, but is not performed on all sites, with some sites using generic relationships presented in literature. Using the strong ground motion relationship and the properties of an event, the theoretical strong ground motion experienced at an excavation is often calculated to assess the effect of large remote events on excavation (Figure 46).
Line 149: Line 152:
Figure 46 Theoretical experienced ppv ground motion experienced  
Figure 46 Theoretical experienced ppv ground motion experienced  


=== 6.5.2 SGM interpolation – advanced ===
=== 6.5.2 Advanced ===


Advanced practice includes regular updates of the strong ground motion relationship. Interpolation of the strong ground motion on a real time basis is currently under development and shows promise as a monitoring tool for the purpose of triggering an action.
Advanced practice includes regular updates of the strong ground motion relationship. Interpolation of the strong ground motion on a real time basis is currently under development and shows promise as a monitoring tool for the purpose of triggering an action.

Revision as of 16:18, 6 July 2018

The seismic analysis step is where the seismic data is used to assess the seismic hazard and to understand the sources of seismicity and response to mining. The assessment of seismic hazard is generally divided into analysis techniques for short term seismic responses (short term seismic hazard) and medium- to long-term seismic hazard assessment techniques. Seismic analysis is also used to investigate seismic sources and mechanisms to increase the understanding of the rock mass response to mining.

Short-term seismic hazard focuses on two components; namely:

  • quantifying elelevated seismicity and its decay after blasts and large events, and, analysis of seismic responses often refered to as “Omori analysis”; and
  • the detection of change in seismicity resulting in short term elevated seismic hazard, i.e time series analysis.

6.1 Short term seismic hazard assessment

6.1.1 Basic

For the analysis of seismic responses after blasts and large events, the basic approaches include the qualitative assessment of a time series chart (e.g. magnitude-time, daily histogram, cumulative event count) and spatial plot of seismicity (e.g. plan view, 3D view). This style of analysis is done on the vast majority of sites irrespective whether more advanced approaches are also considered. Figure 33 provides an example of a seismic response to a large event. Spatial plot is shown left and an annotated time series is shown right (Vallejos and McKinnon 2010).

Figure 33 A spatial plot a) and cumulative event count time seires b) for a seismic response to a large seismic event (Vallejos and McKinnon 2010)

Additionally, the time of day of events is commonly used to evaluate to what degree seismicity is related to blasting; specifically, to estimate the rate of seismicity that occurs independent of blasting (background rate). Figure 34 provides an example of a diurnal chart (Vallejos and McKinnon 2010).

Figure 34 Diurnal chart of seismic and blast activity (Vallejos and McKinnon 2010)

6.1.2 Advanced

Advanced analysis of seismic responses incorporates seismic source parameters into the assessment and/or aims to quantify the space-time characteristics of a response. Temporal assessment of seismic responses can incorporate the location of events by defining an analysis volume. These are arbitrary volumes often defined by coordinates (Figure 35) or by only considering events within a certain distance from a blast.

Figure 35 Spatial volumes (green frames/polygons) are defined with respect to mine surveys a) or elipsoids around blast locations b) to intoduce a spatial component to temporal analysis

The most common method of incorporating seismic source parameters is to consider a rate or accumulation of a parameter value over time.

Advanced analysis also aims to quantify seismic responses by fitting a temporal model to event occurrence. This model is most commonly the Modified Omori Law (MOL) which was derived from the study of earthquake aftershocks (Omori 1894); for example, Figure 36 shows the MOL which models five responses to blasting (Plenkers et al. 2010). Temporal modelling approaches incorporate the location of events by either considering arbitrary areas of a mine, volumes around blasts, clusters determined visually, or clustered determined by an algorithm.

Figure 36 Application of the MOL to seismic responses following blasting. Seismic event rate is plotted with respect to the fitted model and background rate of seismicity

Time series analysis aims at detecting anomalous seismic behaviour as a precursor to elevated seismic hazard. These types of assessments are often used in conjunction with each other. One of the most common approaches is to examine energy-index and cumulative apparent volume, Schmidt Number and extraction induced seismic strain, over time (Figure 37 and Figure 38). Other approaches include cumulative energy, apparent stress time history, ratio of s-wave energy to p-wave energy, static stress drop, and dynamic stress drop.

Figure 37 Time history of CAV, EI and Scs for about one month before a m 1.2 at a deep gold mine in South Africa (Rebuli and van Aswegen 2013)

Figure 38 Time history of CAV, cumulative production and EISSr for about one month before a m 1.9. EISSr shows a steady drop a few days before the m 1.9 event (Rebuli and van Aswegen 2013)

6.2 Re-entry analysis

6.2.1 Basic

The topic of re-entry is covered in two sections. This section focuses on the analysis of data following blasts and large events and the derivation of rules. The application of these rules and real-time monitoring of seismicity and re-entry decisions is discussed under the Control section (10.1.2). For many sites, re-entry protocols are not based on back analysis of seismicity, but rather on choosing conservative re-entry periods. Some sites with enough flexibility in the mining schedule allow long periods before re-entry by sheduling work to be performed in areas further away from recent blasts.

6.2.2 Advanced

Re-entry analysis uses short-term assessment techniques to characterise current and/or historical seismic responses. Blanket exclusion rules are developed from historical responses and consider practical operational constraints. These rules are typically conservative by design and use the assessment of a current seismic response to refined exclusions. Cumulative event count: count of the events that occur within a fixed analysis period (e.g. six hours after) and distance (e.g. 50 m) from blast. Re-entry protocol length is based on an arbitrary event percent for historical responses; for example, protocols are lifted when 90% of events occurred for historical responses.

Seismic event rate – Return to background: re-entry protocols are lifted when the rate of seismicity returns to a previously determined background rate. This is evaluated in several ways ranging from qualitative assessment (e.g. when the slope of cumulative events looks similar to that prior to the blast) to quantitative assessment. IMS STAT is an example where such analysis is performed in real time and translated to a traffic light system for real-time assessment for re-entry times.

6.3 Medium/long term hazard assessment

6.3.1 Basic

Seismic hazard over the longer term is generally reported using simple statistics. Weekly and monthly reports usually include the total number of events recorded, as well as the number of large/significant events. Sometimes the event count over the previous reporting periods is included for reference.

The cumulative number of events is usually used to assess changes in seismic activity rate over time; higher gradients generally representing periods of elevated hazard. The areas within the mine with elevated hazard are often evaluated with event density plots. Event density isosurfaces (Figure 39) are plotted based on an event count within a certain radius. Sometimes a threshold event magnitude is applied to the event count to reduce the effect of varying seismic system sensitivity across the mine.

Figure 39 Example of a seismic event density plot

The frequency-magnitude chart (Figure 40) is used to quantify and visualise the size distribution of events. Many operations use the magnitude where the Gutenberg-Richter relationship at N = 1 (sometimes referred to as the a/b value) as an estimate of medium/long term hazard although in some cases there might not be a sufficient appreciation of the importance of accounting for scale effects in both space and time.

Figure 40 Example frequency-magnitude chart, Gutenberg-Richter distribution and probabilistic hazard

Another basic approach to seismic hazard assessment is to use a simple linguistic scale. The Seismic Hazard Scale in Table 4 uses a derivation of the Gutenberg-Richter relationship to represent the seismic hazard in terms of a single Richter Magnitude seismic event or a qualitative description. The Rosebery mine uses an adapted form of the Seismic Hazard Scale to track seismic hazard. The qualitative description of the scale is used to communicate the seismic hazard more effectively with underground personnel and mine management.

Table 4 Qualitative seismic hazard scale (Hudyma and Potvin 2004)

6.3.2 Advanced

Although the investigation into pre-cursors to earthquakes and mining-induced seismic events are continuing, it is well recognised that meaningful predictions of large seismic seismic events are not currently possible. Given the inherent variability and uncertainty of mining seismicity, results from advanced seismic hazard assessments are often probabilistic (Figure 41).

Figure 41 a) Size distribution plot and the observed (blue dots) and theoretical (solid red) distribution for a section of the mine; b) Probability that PGV >= 0.06 m/s will occur for a section of the mine (after Mendecki 2017)

Some form of probabilistic seismic hazard (PSHA) is now increasingly used in the industry with 87% of online survey responders saying they have used the grid-based PSHA as shown in Figure 42 within the last 12 months. The grid-based hazard assessent quantifies the current hazard state based on the recent historical data. Seismic hazard is calculated probabilisticaly and expressed as hazard ratings and as probabilistic hazard maps.

Figure 42 Example grid-based PSHA map at the Cadia Valley Operation

The seismic hazard for mine development is often expressed as the probability of exceeding a design peak particle velocity (PPV) within a defined time period. The estimation of seismic hazard in terms of PPV requires a site ground motion prediction equation (GMPE) to calculate the magnitude of the ground motion based on the distance and seismic event source parameters (Figure 43).

Figure 43 Example PPV hazard map at the Cadia Valley Operation mine

The PPV map in Figure 43 uses the grid-based results to perform the probabilistic evaluation of PPV’s on the development. This approach estimates the current seismic hazard based on recently recorded data. The Peak Ground Velocity PGV (note that PPV and PGV is the same) map in Figure 44 incorporates modelling information to estimate ground motions for the future mining geometry.

Figure 44 PGV maps from Salamon-Linkov modelling (Malovichko)

6.4 Medium/long term source characterisation

6.4.1 Basic

It is important for the site geotechnical team to form an appreciation of the different sources of seismicity in the mine, their characteristics and their likely response to mining activity. This appreciation is obtained through back-analysis and detailed investigation into the recorded seismic and non-seismic data, interpreting different source parameters within the context of mining. In spite of its importance, this is not commonly done.

Some operations use the S:P energy ratio as an indication of seismic mechanism. High ratios, in theory, indicate a stronger shearing/deviatoric mechanism while lower ratios indicate a more crushing/ bursting/isotropic mechanism. Recent research has raised some doubt over the reliability of the S:P energy ratio parameter (Morkel et al. 2017 Under review).

6.4.2 Advanced

Methods used for medium/long term characterisation of seismic sources analyse seismic data in order to gain insight into the rock mass response to mining; either causation or mechanism of rock mass deformation. The use of moment tensor solutions is becoming more common but, based on the survey conducted, this is only done on an event-by-event basis. Generally, the fault plane of the moment tensor solution is compared with nearby geological orientations. It is less common for operations to use the moment tensor decomposition.

Volume/Polygon-based assessements of source parameters are sometimes performed to quantify the rock mass behaviour in a specified volume. The evaluation of Energy index (EI) and Apparent stress is often used as an indicator of stress, cumulative apparent volume, or the cube root of moment as an indicator of co-seismic rock mass strain and b-value as an indicator of fracture mechanism.

Grid-based analysis is becoming more popular as a seismic analysis tool and is being used by 87% of survey responders. The grid-based approach does not rely on user-chosen analysis volumes and is free of bias due to user-decision on volume selection. It still requires user input, so it is not free of user influence.

An example of a grid-based approach is shown in Figure 45 which shows the results of grid-based analysis of the Energy Index (EI) and Seismic Displacement parameters. In this case, EI is used as a proxy for the stress state of the rock mass and the seismic displacement used as a proxy for damage. This analysis provides valuable indications as to the state of the rock mass and the response to mining activity.

Figure 45 Grid-based analysis of EI and Seismic Displacement (Wesseloo et al. 2014)

6.5 SGM interpolation

6.5.1 Basic

Strong ground motion (PPV or PPA) is often used as a parameter for seismic hazard intensity. The derivation of site-specific relationships is required. This is becoming more common, but is not performed on all sites, with some sites using generic relationships presented in literature. Using the strong ground motion relationship and the properties of an event, the theoretical strong ground motion experienced at an excavation is often calculated to assess the effect of large remote events on excavation (Figure 46).

Figure 46 Theoretical experienced ppv ground motion experienced

6.5.2 Advanced